The Federal Energy Regulatory Commission (FERC) plans to issue its environmental assessment (EA) of the North Extension Project on March 26, 2027. Federal agencies then have until June 24, 2027 to make their authorization decisions. The EA will carry a 30-day comment period.

Natural Gas Pipeline Company of America, LLC (Natural) and Horizon Pipeline Company, LLC (Horizon) filed the application on August 12, 2026 in Docket No. CP26-564-000. They are asking for a Certificate of Public Convenience and Necessity under Section 7(c) of the Natural Gas Act. The project would provide up to 185,000 dekatherms per day of incremental firm natural gas transportation service to Wisconsin Electric Power Company in Kenosha County, Wisconsin. FERC issued its Notice of Application on August 19, 2026.

What the project would build

The plan covers compression in Illinois and a short lateral into Wisconsin:

  • A new 11,107 horsepower compressor station, CS 119, in Lake County, Illinois.
  • A new 31,900 horsepower compression unit at the existing CS 312 in Livington County, Illinois, plus re-wheeling of the existing compressor unit 1 there.
  • A new 11,107 horsepower compressor unit at the existing CS 113 in Will County, Illinois.
  • About 11.5 miles of new pipeline lateral, running from Lake County, Illinois to Kenosha County, Wisconsin.
  • A new meter station at the end of the lateral, along with auxiliary facilities.

Scoping comments

FERC issued a Notice of Scoping on September 22, 2026, and one comment came back. The commenters raised effects and mitigation for birds, bats and sensitive or rare habitats, along with cumulative effects given nearby land use. FERC says all substantive comments will be addressed in the EA.

The 90-day deadline applies to other federal agencies, and to state agencies acting under federally delegated authority, that must act on permits and approvals for the project. FERC says it will give additional notice if the schedule changes.