Drilling has started on Coral North, the second floating LNG project in Mozambique's Rovuma Basin, and the first offshore campaign there to put a company with Mozambican participation in the operator's seat on the rig. Eni and its Area 4 partners announced the start of the drilling and completion campaign, which keeps the project on its schedule for startup in 2028.
The campaign
The work is expected to take about 10 months. ENH-Saipem Drilling Company SA is carrying it out with the SAIPEM 12000 drilling vessel. The wells support the Coral North Floating Liquefied Natural Gas (FLNG) Project, which sits in the northern part of the Coral reservoir in Area 4 of the Rovuma Basin.
The partners with Eni in Area 4 are China National Petroleum Corporation (CNPC), ENH, KOGAS and XRG.
Local content
The ENH-Saipem joint venture takes a direct operational role in offshore drilling, which Eni describes as one of the most technically demanding and capital-intensive parts of the gas value chain. It is the first time a company with Mozambican participation has done so. Eni calls the joint venture's participation a landmark for local content in the country's hydrocarbons sector.
Output and resource base
Eni says Coral North, building on Coral South FLNG, will bring Mozambique's LNG output to 7 MTPA. Coral South was the first project to produce gas from the Rovuma Basin, and it has delivered more than 175 LNG cargoes to the market.
Eni has been in Mozambique since 2006. Between 2011 and 2014 it discovered gas in the Coral, Mamba Complex and Agulha reservoirs, with around 2,400 billion cubic meters in place.
The read for operators and LNG buyers is about sequencing. The wells come first, and a floating unit cannot start up until they are drilled and completed, so a 10-month campaign ahead of a 2028 startup is the step that makes that date concrete.