Five U.S. regional grid operators filed tariff reforms with the Federal Energy Regulatory Commission on Nov. 13 and 16 that would change how data centers and other large electricity consumers connect to the transmission system, secure access to generating capacity and pay for new infrastructure. The filings respond to FERC's June 18 show-cause orders. The operators appear willing to adopt a 50-MW threshold to define a large load, but their proposals differ sharply on the conditions for transmission service, the capacity a customer must secure, and the operational and financial obligations it would take on.

What FERC asked for

FERC opened six proceedings on June 18 under Section 206 of the Federal Power Act, after preliminarily finding that existing regional transmission tariffs may be unjust and unreasonable, or unduly discriminatory or preferential, in how they treat large loads. The orders named five areas for reform: efficient transmission service studies, rules for co-located loads and loads served by behind-the-meter generation, transmission services for flexible loads, studies of generating facilities serving electrically proximate large loads and co-located loads, and transparency in infrastructure costs and cost allocation. FERC also directed each operator to address separately how it will ensure enough generation capacity for existing and new large loads.

On Aug. 14, the Commission held the show-cause proceedings in abeyance to make room for the filings. ISO New England filed Nov. 13. The California Independent System Operator (CAISO), the Midcontinent Independent System Operator (MISO), the New York Independent System Operator (NYISO), PJM Interconnection and PJM's transmission owners followed on Nov. 16. Southwest Power Pool's deadline is Nov. 20.

The June orders also advance an Oct. 23, 2025, directive from Energy Secretary Chris Wright, who invoked Section 403 of the Department of Energy Organization Act to start rulemaking on large-load interconnection to the interstate transmission system. FERC chose region-specific reforms and kept that rulemaking open as Docket No. RM26-4-000.

Non-firm service and price triggers

The most notable change is a wider set of transmission service options that could let large loads draw power on a non-firm basis, potentially before all the network upgrades needed for firm service are finished. MISO, NYISO and ISO-NE each proposed mechanisms that use wholesale electricity prices to trigger cuts in grid withdrawals. Thresholds, market mechanics and capacity obligations differ among the three.

MISO's Grid Responsive Integration Transmission Service, or GRITS, would be an ongoing alternative to conventional network service. MISO's example is a 500-MW facility that takes 200 MW of firm service and up to 300 MW of non-firm service under one agreement. Firm GRITS could be reserved for at least one year, and non-firm GRITS for one day to one month. Non-firm demand would be interrupted when the locational marginal price at its commercial pricing node exceeds $100/MWh. MISO also proposed an Interim Network Integration Transmission Service, which would let a load start with a mix of firm and non-firm service and convert portions to firm as transmission capability becomes available.

Capacity requirements and PJM's process

The resource adequacy proposals split further. ISO-NE's "Bring Your Own New Capacity" requirement would make large loads seeking firm transmission service secure incremental new capacity. NYISO would let large loads whose addition would adversely affect resource adequacy obtain firm withdrawal rights through long-term arrangements with qualifying resources that need not be co-located. CAISO argues that a customer-specific generation procurement requirement is unnecessary under its existing resource adequacy framework. It proposed a Flexible Interim Load Interconnection arrangement for earlier energization subject to transmission constraints.

PJM proposed a Fast Energization Process that would fold generation interconnection and large-load transmission service studies into a single 12-month cycle. In a separate filing it proposed ride-through requirements, which set thresholds for data centers to stay connected to the grid instead of switching to backup generation. PJM's transmission owners proposed a methodology to spread the cost of the resulting transmission reinforcements among transmission customers and generation developers.

All of the proposals remain subject to FERC review. Several of the larger reforms would need further tariff filings, stakeholder proceedings or market software development before they could take effect.