Hilcorp Alaska can drill three new wells on K Pad in the Beluga River unit after Alaska's Division of Oil and Gas approved an amended unit plan of operations on 18 August. The company applied for the change on 4 August, saying the new wells would raise gas output from the unit.

The wells target state subsurface lease ADL 21128, within the unit on Cook Inlet's west side, about two miles west of where the Beluga River meets the inlet. The work adds to Hilcorp's upstream activity in Cook Inlet.

Equipment set to go on the pad for drilling and well testing includes:

  • A drill rig and pipe
  • A completion rig
  • Mud tanks and pumps
  • Boilers, generators and cement silos
  • A line heater and a liquids/gas separator
  • A flare and a 400-barrel water tank