PJM filed a proposal with FERC on Monday, Nov. 16, that would require data centers and other large computational loads to stay connected to the grid during transmission disturbances. The grid operator wants new voltage and frequency ride-through requirements to take effect Jan. 16, 2027.

The July 22 event behind the filing

On July 22, nearly 3.9 GW of data centers moved from utility power to their own onsite generators in response to a routine transmission disturbance. PJM says it was the largest load transfer of this kind in its history.

The transfer affected system voltages, frequency, power flows and generator behavior in the Dominion transmission zone and across the Eastern Interconnection. PJM's Control Center managed it safely. Even so, PJM says the size and speed of the transfer posed serious threats to grid reliability and safety. The filing follows several similar events in the PJM region in recent years.

PJM says the proposed ride-through standards would have lessened the grid impacts of the July 22 event had data centers and other large computational loads been built to them and followed them.

A new load category above 50 MW

The filing would define a Large Computational Load (LCL) as a load exceeding 50 MW. PJM says this definition conforms with standards under development by FERC and the North American Electric Reliability Corporation (NERC), and aligns with definitions other grid operators are adopting.

PJM already serves about 10 GW of existing LCL and forecasts additions of up to 30 GW by 2030.

What the tariff amendment would require

The proposal would amend PJM's Tariff in two ways.

  • Any new LCL would have to demonstrate compliance with the requirements as a condition of interconnection and operation.
  • Existing LCLs would have to comply within one year of the effective date or within one year of commercial operation, whichever is later.

PJM says the ride-through requirements are a first step. It plans to keep working with stakeholders to strengthen them, develop ramp-rate requirements and address other reliability-related performance characteristics. Those changes would draw on operating experience, technical studies, and future guidance, standards or directives from NERC or FERC.